Technical Water Treatment Plant
Deadline:N/A
Tender information
Sydjylland
Type
Contract award
Procedure
Negotiated with a call for competition
Evaluation criteria
Price, Quality
Ref. number
3
Estimated value
€45,000,000
This contract notice apply to DIN Forsyning Teknisk Vand A/S' cancellation of the procurement of Technical Water Treatment Plant. Technical Water Treatment Plant is a facility that cleans
purified wastewater for use in Power-to-X facilities.
In Denmark, the declared goal by 2030 of reducing CO2 emissions by 70% to combat climate change has led to an ambitious plan for Power-to-X, i.e. converting green renewable electricity into fuels (and more) for use in the hard-to-abate sectors, such as the industry, heavy transport, aviation, and shipping transport.
DIN Forsyning Teknisk Vand A/S cooperates with companies that want to buy significant quantities of technical water. Technical water is a general term for water that has a different quality than drinking water. The technical water will have a quality as demineralized water.
The procurement comprised the complete delivery of a combined plant consisting of:
Pure Water Treatment Plant; Reject Water Treatment Plant; buildings; and high voltage installations.
The plant is called Technical Water Treatment Plant (TWTP). The TWTP will be located on Mådevej, 6700 Esbjerg. The TWTP must be designed to operate continuously, 24 hours a day, 7 days a week, and 52 weeks a year.
The project will be divided in two phases; Phase 1 and Phase 2. Phase 2 is included as an option.
The initial phase (Phase 1) will support approximately half of the total capacity.
Project capacity: Phase 1 must have a capacity of 230 m³/h output.
Phase 2 (option) must have a capacity of 230 m³/h output.
The project including the optional Phase 2 must have a capacity of 460 m3/h output.
This project also includes a contract for underground piping which is offered in another procurement. DIN Forsyning Teknisk Vand A/S has chosen not to divide the project/contracts further. DIN Forsyning Teknisk Vand A/S has assessed that handling interfaces, responsibilities and risks in particular the contract for TWTP is best placed with the contractor. Further division of the project /contracts will entail increased risk for DIN Forsyning Teknisk Vand A/S, as well as increased costs for construction management etc., which is why DIN Forsyning Teknisk Vand A/S has found it appropriate not to divide the project/contracts further.
Buyer
DIN Forsyning Teknisk Vand A/S
Documents
Buyer
DIN Forsyning Teknisk Vand A/S
Cancelled
Important dates
8 Sept - Publication date
Unlock Full Access with Mercell Bidding Business Plus