GRIP 5-8 Delivery of Coventry South, Northampton CET and Tyseley Fuel Road 12
Deadline:N/A
Summary
Tender information
Coventry
West Northamptonshire
Birmingham
Type
Contract
Procedure
Not given
Ref. number
DfTO3839
Estimated value
£36,600,000
Duration
31/05/2027 - 31/12/2027
WM Trains Limited is procuring rail depot and servicing works through one advertised works procurement structured in two contractual stages.
Stage 1: PCSA
Under the Pre-Construction Services Agreement (PCSA), the contractor will complete the GRIP 5 design, further develop the design, and price the individual works packages.
Stage 2: ECC
Once those package prices have been developed and consolidated into a single commercial position, the project will proceed to award the NEC4 Engineering and Construction Contract (ECC) on a lump-sum basis for GRIP stages 6 - 8.
The procurement is intended to appoint a contractor for each Lot to provide Stage 1 PCSA services. Stage 2 may follow, subject to the contracting authority´s decision, funding, approvals and procurement compliance requirements. The contracting authority does not commit by this notice to award Stage 2.
Please note that it may not be necessary for the successful bidder for each Lot at Stage 1 to undertake all of the GRIP 5 design required for that particular Lot as some elements of the GRIP 5 design may already have been completed by tender award stage. If that is the case, it would be expected that the successful bidder would inherit any GRIP 5 design already completed for a particular Lot and then use that to inform the remainder of the GRIP 5 design required for that particular Lot.
The procurement is divided into the following Lots:
Lot 1 - Coventry Carriage Sidings Stabling and Servicing Facility
Lot 2 - Northampton Riverside CET
Lot 3 - Tyseley Road 12 Permanent Fuelling Apron
Tenders may be submitted for one, more than one, or all Lots, subject to the instructions in the associated procurement documents available at https://www.delta-esourcing.com/respond/EHTJX59C3V.
For more information about this opportunity, please visit the Delta eSourcing portal at:
https://www.delta-esourcing.com/tenders/UK-UK-Birmingham:-Railway-depot-construction-work./EHTJX59C3V
To respond to this opportunity, please click here:
https://www.delta-esourcing.com/respond/EHTJX59C3V
Please note that the contract start and end dates given for each Lot are provisional and are to be agreed following submission of programmes at the ITN stage. The dates are purely draft and are a guide only ahead of the procurement commencing and may be considerably longer than stated. The start date for each Lot may vary dependent on the availability of GRIP 4 design and not all contracts may be awarded at the same time and not all ITN´s issued at the same time following shortlisting at the PSQ stage.
–
Lot nr.: 1
Coventry Carriage Sidings Stabling and Servicing Facility
Coventry Carriage Sidings are located immediately south of Coventry Station adjacent to the Leamington Line and currently comprise four sidings with limited operational use. The sidings are currently classified as Network Rail sidings and only Roads 3 and 4 are presently accessible due to track materials being stored on Roads 1 and 2. Live OHLE infrastructure is present at the entrance to the sidings and on the adjacent main line.
It is intended to develop the sidings into an operational stabling and light maintenance facility to support the Class 730 fleet and future operational requirements associated with the Coventry and Snow Hill routes.
The project shall provide overnight stabling capacity for up to ten 3-car Class 730 units together with servicing infrastructure including CET, tanking, cleaning, walking routes, welfare facilities, lighting, security, electrical infrastructure and operational safety systems.
The development is expected to require significant civils, track, M&E, drainage, OHLE, operational safety and depot infrastructure works. The proposed changes are also expected to require the sidings to be reclassified as a Light Maintenance Depot, subject to Network Rail approvals.
The project will also improve operational access to the sidings through reinstatement of the disused walking route from Platform 4 and associated access, security and lighting upgrades.
Duration contract start date : 31/05/2027 11:00:00 PM
Duration contract end date : 31/12/2027 11:59:59 PM
Criteria definitions: Price: 35 (Price)
Quality: 65 (Quality)
–
Lot nr.: 2
Northampton Riverside CET
The Train Presentation Team currently undertake the evacuation of Controlled Emission Toilets and tanking on the 4-car Class 350 units using mobile bowser units whilst trains are dwelling at Northampton Station on Platforms 1, 2 and 3. These mobile units are then discharged by connecting to a discharge point located near the south end of bay platform 4 or the north end of platform 2.
Whilst these facilities are suitable for CET maintenance activities on the Class 350 units, they are not suitable for evacuating the CET on the new Class 730 units as the connection points are located below the sole bar and cannot be accessed from the platform.
This project scope is to provide the facilities required by the Train Presentation Team to undertake both CET and train servicing activities and for drivers to safely access and egress the trains when stabled in Northampton Riverside Sidings A and B.
To support these activities, WM Trains have created a Light Maintenance Depot at Northampton within which the following activities will be undertaken overnight on the Class 730 trains stabled in the river sidings:
CET extraction, flushing and tanking
waste removal
internal cleaning
topping up of screen wash
pre-train operation inspections
front end cleaning, where required
topping up of train sand boxes, where required
Duration contract start date : 31/05/2027 11:00:00 PM
Duration contract end date : 31/12/2027 11:59:59 PM
Criteria definitions: Price: 35 (Price)
Quality: 65 (Quality)
–
Lot nr.: 3
Tyseley Road 12 Permanent Fuelling Apron
WM Trains currently operates fuelling and train servicing activities at Tyseley Train Maintenance Depot, Birmingham using existing permanent fuelling roads 13, 14 and 15. Following operational changes associated with fleet deployment, revised timetable requirements and depot operational constraints, the temporary fuelling arrangements installed on Road 12 during previous fuelling enhancement works have become operationally critical.
The project will provide a permanent embedded track fuel apron and associated servicing infrastructure on Road 12 to replace the temporary arrangements.
The proposed project will provide a permanent embedded track fuel apron, associated below ground drainage and interceptor systems, fuelling and servicing facilities, canopy structures, depot protection interfaces, lighting, CCTV, M&E infrastructure and associated operational facilities.
The project shall support the safe and efficient servicing of up to 6-vehicle formations without splitting or shunting and shall be designed to accommodate current and future operational requirements.
Duration contract start date : 31/05/2027 11:00:00 PM
Duration contract end date : 31/12/2027 11:59:59 PM
Criteria definitions: Price: 35 (Price)
Quality: 65 (Quality)