BA-26-023-GK Project reserve water Gjøvik-Biri ENT1B Raw water pump station (V2).
Deadline:21 Aug 2026, 11:00
Tender information
Innlandet
Type
Contract
Procedure
Negotiated with a call for competition
Ref. number
6743
Estimated value
NOK 95,000,000
Duration
46 months
Gjøvik municipality is responsible for ensuring a safe and stable delivery of drinking water to the inhabitants of the municipality. In order to strengthen security of supply, it has been decided to establish a full-fledged back-up water system that can supply both Biri and Gjøvik.
Stage 1 of the project included the establishment of an submarine pipeline from Gjøvik to Redalen, the construction of a pressure increase station, as well as establishing a connection point for continuing the pipeline towards Biri. The sea pipeline was lowered in Mjøsa in autumn 2020, and after completion of the pump station the facility was put into operation in 2021.
In stage 2 the pipeline shall be continued from Redalen to Biri, where both a raw water pump station and a new water treatment plant shall be established.
In this contract, the establishment of a raw water pump station with the execution of pipelines from ENT2 up until the land pipeline contract ("ENT3") shall be executed.
Buyer
Gjøvik Kommune
Documents
Buyer
Gjøvik Kommune
No time limit
40 days left
Important dates
10 Jul - Publication date
21 Aug - Deadline