NWFC | Mobilising System Solution Procurement
****1 | Since commencement of the contract there have been delays to development and implementation and as a result the delivery of the contract is expected to be delayed as set out. Milestone Number - Milestone Title [Contractual Date / Anticipated Delay Date]. 1 - Detailed Implementation Plan and Project Start-Up Documentation [11-Jul-25 / 3-Aug-26]. 2 - Installation/setup, commissioning and configuration, plus Testing [18-Nov-25 / 3-Sep-26]. 3 - Satisfactory Completion of Integration testing[6-Feb-26 /19-Apr-27]. 4 - Site Acceptance Test (SAT) complete [4-Mar-26 / 26-Aug-27]. 5 - Readiness for service (data migration (and Testing), training and go live) [1-Apr-26 / 16-Sep-27]. 6 - 3 months live operation with no Major Faults [1-Jul-26 / 23-Dec-27]. It is not proposed that that as a result of these delays there will be any modifications to the Contract. Rather the delay will be shown in the Detailed Implementation Plan as 'Anticipated Delay'.